Project #: | 24-06 |
Detailed Status: | Stage II Design |
Building Gross Sq. Ft: | 9,567 |
Campus: | MSU Wichita Falls |
Location: | 2480 Comanche Trail (911 use only) All MSU buildings use 3410 Taft address |
Budget |
Board Approved Budget: | $387,073 |
Adjusted Budget: | $387,073 |
Schedule |
Project Start Date: | 07.01.2024 |
Project Team |
Program Director: | Denise Hostick |
Field Observer: | Kyle Owen |
Design Professionals: | Bundy, Young, Sims, Potter, Inc. (BYSParchitects) |
CM Agent: | n/a |
Description |
The Daniel Building was renovated into the new Bridwell Activities Center and made available for student use in August 2022. The project remodeled the first floor only. Funding was not available for renovation of any part of the second floor at that time until now.
The second-floor total area available for renovation is 17,600 GSF with approximately 11,000 GSF to be utilized by the student success initiative and military partnership; the remaining 6,600 GSF will be for future expansion.
The programming phase of the project will define the specific needs of each group as they move forward on the project. |